Cleared Area as contractor or leading partner – 35,879.726 square meters
Mine Clearance – 10,743.698
Technical Survey – 5,136.028
Cleared Area as subcontractor or partner – 10,314.749 square meters
Mine Clearance – 4,108.125
Technical Survey – 1,206.624
Mines and UXO
Removed and disposed mines – 8.741 pieces
UXO – 53.381
Other, unindentified ERW – 76
Battle Area Clearance Projects in Croatia are so far included in Mine Clearance. Operational Methodology is the same, according to the Law and Rules in Croatia. We estimated there is no more than 5% BAC Cleared Area in Mine Clearance.